Last Friday we learned of yet another neat green feature in our house. On top of cool things like solar panels, geothermal heating and cooling, a hot water recovery stack, on-demand water heating, 2" foundation foam, tiles made out of recycled light bulbs, and others, we have a LaundryPure laundry system.
LaundryPure is a small gadget that mounts to the wall behind almost any regular washing machine and eliminates the need for detergent, fabric softeners, bleach, and hot water. Cold water goes to the LaundryPure first and UV light bulbs oxidize it eliminating the need for detergent. Oxygen and peroxides lift dirt and odors away from clothes. Clothes are supposed to become softer, fluffier, and last longer.
More info and a demonstration can be seen here.
I have to admit I'm a bit skeptical but hopeful. I'll post again after I've used it!
Wednesday, August 18, 2010
Sunday, August 8, 2010
The Home Stretch
A lot has happened in the past 3 weeks. The Trend Home will be unveiled August 13th in the VHBA Summer Parade of Homes. It's looking phenomenal and we couldn't be more excited to get in and start pushing buttons!
Here's a sneak peak before the parade:

Here's a sneak peak before the parade:
Labels:
energy management,
exterior,
Solar,
stairwell
Saturday, July 17, 2010
We have the power!
Solar power, that is. Jim & the crew from Energize LLC were at the house wiring & mounting the first solar panels. After these thirty 180 watt photovoltaic panels are connected they will have a significant impact on the home's energy cost - especially since the home is all-electric.

Driveway & Trim Finishing
Wednesday, July 14, 2010
Solar, Sinks, Newels, and Retaining Wall
The house is a-buzz with work today! There's all kinds of stuff going on.
There's a roof crew prepping the solar panel installation. They've installed several sets of rails to house the 30 panels that will soon be powering the house.

The newel posts (Who wanted to learn a new word today? That means posts at the bottom and tops of staircases.) have gone in.


All sinks and plumbing accessories (towel bars, toilet paper holders, etc.) are being installed.
Kitchen sink

Powder room sink downstairs

Main bath sinks upstairs

Master bath sink (there are 2 of these)

And the retaining wall in the backyard was done on Monday.

Next on the list - landscaping and staircase hand rails!
There's a roof crew prepping the solar panel installation. They've installed several sets of rails to house the 30 panels that will soon be powering the house.
The newel posts (Who wanted to learn a new word today? That means posts at the bottom and tops of staircases.) have gone in.
All sinks and plumbing accessories (towel bars, toilet paper holders, etc.) are being installed.
Kitchen sink
Powder room sink downstairs
Main bath sinks upstairs
Master bath sink (there are 2 of these)
And the retaining wall in the backyard was done on Monday.
Next on the list - landscaping and staircase hand rails!
Friday, July 9, 2010
Geothermal Ground Loop
Yesterday the ground loop for the geothermal heating and cooling system was installed. The system will circulate water through 3 sets of tubing laid approximately 8' underground (below the frost barrier) and use this to heat and cool the home. Pretty cool - and green!
The giant hole in the backyard dug for the loop

The loop is comprised of three 1-ton coils

The dirt was replaced after installation was complete

Also installed recently was a heat-recovery stack designed to capture heat from hot water (think showers, dishwater, washing machine) going down the drain.

Our geothermal heat pump and auxilliary water heater.
The giant hole in the backyard dug for the loop
The loop is comprised of three 1-ton coils
The dirt was replaced after installation was complete
Also installed recently was a heat-recovery stack designed to capture heat from hot water (think showers, dishwater, washing machine) going down the drain.
Our geothermal heat pump and auxilliary water heater.
Labels:
geothermal,
ground loop,
heat recovery stack
Finish Carpentry, Fireplace, and Lighting
The house's finish carpentry is now nearly complete, most light fixtures are installed, and the fireplace stonework and mantle are done.
Stairway caps and skirt boards are installed

Fireplace and mantle

Master bedroom tray ceiling with molding installed

Master bath lighting

Powder room lighting (obviously only 1 of 2 fixtures)

Upstairs main bath lighting

Exterior lighting on garage
Stairway caps and skirt boards are installed
Fireplace and mantle
Master bedroom tray ceiling with molding installed
Master bath lighting
Powder room lighting (obviously only 1 of 2 fixtures)
Upstairs main bath lighting
Exterior lighting on garage